Sr. No. |
Description |
Status as on 31.07.2010 |
|
1 |
Geological Exploration Comprising Surface Mapping, Drilling and Drift works |
Drilling Package-I (Barrage): Out of 335 m ,163.5m is completed. Package-II (For PH Site): Work for 5 holes involving 780m length awarded on 05.06.10 and target date for completion is 30.11.10.Mobilisation not yet started by the Contractor due to road blockage.
Drifting (Power house, Barrage site & Desilting Chamber) 3 locations-780m :- LOA issued on 19.06.10. The work is to be finished within 9 months i.e. April,11. Mobilisation not yet started by the Contractor due to road blockage. |
|
2 |
EIA studies and EMP |
The report finalized after R&R provision. Identification of land and PAFs
is in progress. |
|
3 |
Preparation of DPR |
Necessary data of drilling & drifting is being explored for the preparation of DPR. |
|
4 |
Topographic survey |
Survey work awarded on 20.03.2010 and is in progress. All Project components except desilting complex have been marked on ground. Identification & measurement of dumping sites & contractor's facilities is in progress. |
|
5 |
Submission of application for diversion of Forest land & Govt. land. |
Submission of application for diversion of Forest Land planned by 30.09.10. Target date for all land identification for Dumping area and other facilities is 31.08.10 |
|
6 |
Acquisition of Private land required for execution of the project |
Award for survey of the land made on 20.03.10 and work is in progress. Identification of private land will start after completion of the survey. Marking of Land required for execution of project planned by 31.08.10. |
|
7 |
Arrangement of construction power |
Estimate sanctioned for 2 DG sets but now requirement is to buy 1 DG set . |
|
8 |
Gauge & Discharge sites |
Recording is being done regularly since 20.03.2010. |
|
9 |
Hydro-Meterological observations |
Recording is being done regularly using (Computerized) Weather Station. |
|
10 |
Collection of silt data and its analysis |
Regular collection of silt samples has been in progress since 17.07.06.
|
|
11 |
Mining Clearance |
Quarry site inspected by SDO, Forest Deptt. on 24/04/10. Report yet to be submitted by him. Matter is being pursued. |